Lakeview Parkway/Provo Westside Connector Construction Update - October 19, 2016


The Road is Open!

The Lakeview Parkway/Provo Westside Connector is now officially open, as well as the northbound on-ramp coming off of University Avenue. Thank you for your patience during construction.

Crews are currently working to finish up a few remaining details along the project, but traffic should not be affected.

Crews will also be planting trees and seeding the wetland area south of the road.

Be aware that a planned, controlled burn of weeds will be occurring near the end of October/beginning of November. If you drive in the area during the burn, please be extra attentive as other drivers may be distracted by the flames and smoke.




Contact Us

Public Information Team

To receive e-mail construction updates, please send an e-mail with “Updates” in the subject line to:

For questions, concerns or updates, please contact us:
Phone: 1-800-653-4255



Project Background

Provo City, in partnership with the Utah Department of Transportation (UDOT), is constructing a new 3-mile roadway connection between Interstate 15 and the Provo Airport.

Phase 1 began in May 2014. This phase of the project included earthwork, drainage and structure work between 500 West and I-15.

Phase 2 of the project began in September of 2014 and will complete the road between I-15 and the airport.

Benefits of the Westside Connector will include better access to Provo on the west side of I-15 and will provide a more convenient route to the airport.